Dining rooms, commercial kitchens, and full restaurant build-outs, built to health code and to your opening date by a licensed contractor who knows dark days cost money.
Restaurants carry requirements almost no other build has all at once: commercial kitchen code, state food-service approval, grease and hood systems, grease interceptors, ADA dining and restrooms, and finishes that survive daily abuse. Miss one and you do not open, and every dark day is rent and payroll with no register ringing.
We build and renovate restaurants across Marion, Sumter, and Lake Counties, coordinating with your kitchen designer, equipment vendors, and the building and state review departments so inspections pass and you open on schedule.
Florida Legacy Construction is a state Certified Building Contractor, license CBC1268994. That license covers commercial buildings up to three stories along with the structural, plumbing, electrical, and mechanical scopes underneath, so a restaurant build-out runs as one contract rather than a handful of specialty contractors trying to coordinate themselves around a hood installation.
Restaurants are part of our broader commercial build-out work, alongside retail build-outs and office space.
This is the single most important thing to understand before you sign a lease or set an opening date. A restaurant renovation in Florida has to clear two independent approval paths, and they are not the same submission, not the same reviewer, and not the same set of forms and fees.
General contractors without restaurant experience treat the building permit as the whole job. It is roughly half of it.
Your county or city building department reviews the construction side of the project.
Florida's Department of Business and Professional Regulation reviews your kitchen against the Florida Food Code and issues your food service license.
We break the numbers down further in our restaurant renovation cost guide for Ocala and The Villages.
Line to dining room, coordinated with your kitchen designer, your equipment vendors, and both approval tracks.
Kitchen build-outs and renovations sized to your menu, with the layout your line actually needs.
Type I and Type II exhaust hoods, make-up air, and grease interceptors built and installed to code and to pass inspection.
Front-of-house spaces, bars, and finishes that hold up to volume and set the room's whole tone.
Surfaces, hand sinks, floor drains, and layouts built to the food-code requirements that gate your license.
Accessible restrooms, entries, and paths of travel that meet code without eating your seat count.
Shell-to-open build-outs coordinated with your equipment vendors, designers, and inspectors.
Slab work, drainage, electrical, and framing for walk-in coolers and freezers, coordinated with your refrigeration vendor.
Covered and uncovered outdoor seating, including the exiting, lighting, and drainage that come with it.
Turning one restaurant concept into another, or converting non-food space into food service, which is where surprise requirements live.
Before anyone can price a restaurant project, the real question is what the space already has. Two suites at the same square footage can be several hundred thousand dollars apart on this alone, and it is worth knowing before the lease is signed rather than after.
A restaurant operated here before you. That can mean an existing hood and make-up air, a grease interceptor, a grease waste line, floor drains, a walk-in pad, and three-phase power already in place. Those are the most expensive items in a food-service build, and inheriting them changes the project completely. Your work becomes layout, finishes, equipment, and bringing anything non-compliant to current code.
No hood, no grease interceptor, no grease waste line, no floor drains, and often no adequate electrical service or gas supply. Every one of those has to be designed, permitted, installed, and inspected, and several of them involve the utility or the sewer authority rather than just the building department. Converting retail or office space into food service is the most expensive version of this project.
Type I hoods over grease-producing equipment carry exhaust, make-up air, fire suppression, and roof work. This is routinely the largest single line item in a kitchen build.
Sizing and requirements are set by the local utility or sewer authority, and an exterior in-ground interceptor is a different project from an under-sink unit. Confirm what your address requires before budgeting.
Commercial kitchen equipment loads regularly exceed what a previous non-food tenant needed. A service upgrade or a new gas run is a five-figure item that turns up at design, not at demo.
Hoods and refrigeration commonly run 8 to 16 weeks. The order date, not the construction schedule, is usually what sets your realistic opening.
Your seat count drives restroom fixture counts, exiting, and sometimes parking. Adding seats late in design can reopen approvals you thought were finished.
The dining room is where concept budgets swing most, and it is also the easiest place to phase if the total comes in high. The kitchen is not.
Which building department reviews your project depends on your exact address rather than your mailing city, and plenty of addresses with Ocala mailing addresses sit in unincorporated Marion County. The DBPR track is statewide and runs the same regardless of which county you are in.
Beyond building and DBPR, a restaurant commonly involves the fire marshal, the local utility or sewer authority for the grease interceptor, and the landlord's own approval where you are in a leased center.
Unincorporated Marion County addresses are reviewed by Marion County Building Safety through the county's online system. Addresses inside Ocala city limits go through City of Ocala Building Services, with Growth Management involved when the use is changing.
Fire review runs alongside building review rather than after it, which is why we submit both together instead of waiting for the first approval.
Sumter County reviews through its own online portal, and the City of Wildwood runs a separate system for addresses inside city limits.
Restaurant space in and around The Villages usually carries a private design review from the developer alongside the public permit, and the community crosses county boundaries, so jurisdiction gets confirmed address by address.
Lake County accepts applications online or on paper, with zoning and land development review happening before building code review. The county does not review work inside incorporated cities, so a Leesburg address goes through the city's own building department.
Impact fees can apply when a change of use increases demand on utilities, sewer, or traffic, and those get confirmed during review rather than quoted flat up front.
On restaurant work the schedule is the product, and the long poles are approvals and equipment rather than construction. Here is the sequence.
We walk the space with you, ideally before the lease is signed. We look for the expensive inheritances: hood, make-up air, grease interceptor and waste line, floor drains, electrical service, and gas. Then we tell you what you are actually inheriting versus building.
We coordinate with your kitchen designer and equipment vendor to lock the line layout and the equipment schedule, because DBPR reviews against that and your electrical and plumbing rough-in depends on it. Pricing develops alongside the design while changes are still free on paper.
Building permit, fire review, and DBPR plan review go in at roughly the same time, along with any landlord approval. Running them in sequence is the single most common reason a restaurant opening slips by months.
Hoods and refrigeration go on order as soon as the schedule is locked, not when the walls are up. With 8 to 16 week lead times common, this is the decision that most often decides whether your opening date is real.
Demo, framing, then mechanical, electrical, plumbing, and fire protection rough-in, sequenced so inspections stack in the right order. Hood and refrigeration set once the space is ready for them rather than the other way around.
Building and fire finals, the certificate of occupancy, and the DBPR licensing inspection. We hand over a space you can legally open and serve in, with time left for staff training and a soft open.
Restaurant bids are the hardest commercial bids to compare, because so much of the cost sits in scopes a first-time operator has never priced. Here is what to actually ask, whether or not you end up hiring us.
This is the fastest way to find out whether a contractor has built restaurants before. If they do not immediately know that DBPR plan review is a separate submission from the building permit, they will learn it on your project and on your lease clock.
Florida licenses are tiered, and not every remodeling contractor can legally run commercial work. Verify the class and number yourself on MyFloridaLicense.com. Ours is CBC1268994, a Certified Building Contractor license covering commercial structures up to three stories.
The answer should be early, before rough-in, with a named lead time. A contractor who plans to order the hood after framing has already added weeks to your opening without telling you.
Restaurant bids differ mostly in exclusions: grease interceptor, electrical service upgrade, gas run, roof work for the hood, fire suppression, equipment setting, and walk-in pad are the usual ones. A cheaper bid almost always means a shorter scope.
Your equipment supplier, kitchen designer, and builder all have to work from the same schedule. Ask who owns that coordination, because when nobody does, the rough-in ends up in the wrong place and gets redone.
Running a retail build-out well does not prove someone can clear a food-service license. Ask for restaurants they have opened, and go eat in one. You can also read our reviews here.
Restaurant work is inspected against building code and reviewed for food-service licensing at the same time. A licensed contractor is how you clear both. Verify license CBC1268994 on MyFloridaLicense.com before hiring anyone, including us.
Our shop is in Ocala and we work a tight radius on purpose. On a restaurant that matters more than on almost any other project, because being twenty minutes away is what lets a crew meet an inspector on short notice instead of losing a day off an opening date.
Marion County is home base. We work on restaurant space downtown, along the SR 200 corridor, and in the plazas and centers spreading across the east and southwest sides of the county.
The practical detail here is jurisdiction. Plenty of restaurant addresses with Ocala mailing addresses are reviewed by Marion County rather than the city, and the two run different systems with different submittal requirements.
Ocala services →Wildwood is a short run up US-301 from the shop and it is growing fast. We have completed commercial kitchen and restaurant renovations here, and this corridor sees steady new food-service space coming online.
Restaurant space in and around The Villages typically carries a private design review from the developer alongside the public permit, with its own standards for storefront, signage, and outdoor dining. The community crosses county lines, so jurisdiction is confirmed per address.
Wildwood services →Lake County work runs through the county for unincorporated addresses and through the individual city for incorporated ones, with Leesburg operating its own building department.
Zoning and land development review happens ahead of building review here, so converting a non-food space into a restaurant needs to start earlier than operators usually expect. We front-load that step rather than discovering it after drawings are done.
Leesburg services →The surrounding communities across Marion, Sumter, and Lake Counties are inside our normal working radius. If you are looking for a restaurant contractor near you and your space is within about an hour of Ocala, call and tell us the concept and the date you want to open. If we are not the right fit, we will say so rather than burn your lease clock finding out.
Both. A Florida restaurant runs through two separate approval tracks: your county or city building department for the construction side, and the DBPR Division of Hotels and Restaurants for the kitchen layout, equipment, plumbing fixtures, and finishes reviewed against the Florida Food Code. We build to both and coordinate both submissions.
Track one is your county or city building department, covering structural, electrical, plumbing, mechanical, and fire protection review, ending in the certificate of occupancy. Track two is DBPR plan review, which is a completely separate submission with its own forms, fees, and reviewer, and it is required for new establishments and significant remodels. They are not the same approval and passing one does not satisfy the other.
Most standard renovations run 4 to 7 months from permit submission to opening, with DBPR plan review and county permitting running in parallel. Full kitchen build-outs and fine dining concepts run longer, largely because hoods and refrigeration commonly carry 8 to 16 week lead times.
A second generation space had a restaurant in it before you, which can mean an existing hood and make-up air, a grease interceptor, a grease waste line, floor drains, a walk-in pad, and adequate power already in place. Those are the most expensive items in a food-service build. A cold shell or a converted retail space has none of them, and every one has to be designed, permitted, installed, and inspected.
It depends far more on what the space already has than on square footage, which is why we do not publish a per-square-foot number. Inheriting a working hood and grease interceptor versus building both from scratch is a difference measured in six figures. We walk the space and give you a written scope and a real price.
Most food service establishments discharging to a sanitary sewer are required to have one, but sizing and the specific requirement are set by your local utility or sewer authority rather than by a single statewide rule. An exterior in-ground interceptor is a very different project from an under-sink unit, so we confirm what your address requires before anything gets budgeted.
Yes, and we prefer to. Restaurant projects go smoothest when the builder, kitchen designer, and equipment supplier all work from the same schedule, because the rough-in locations depend on the equipment schedule. We manage that coordination rather than leaving it to sort itself out.
For a renovation of an operating restaurant, we plan the scope and sequence to keep the closed window as short as the work honestly allows, and we tell you that window up front rather than discovering it together. Where a project can be phased to keep part of the operation running, we will tell you that too.
Generally yes, and you also need your food service license, which is a separate approval. Passing your final building inspection does not mean you can serve food. Both need to be on the schedule from day one, not treated as paperwork at the end.
Yes. We serve Marion, Sumter, and Lake Counties, including Wildwood, The Villages area, Leesburg, Lady Lake, Belleview, Summerfield, and Dunnellon. We keep the radius tight on purpose, because being close enough to meet an inspector on short notice is worth more on a restaurant than on almost any other project.
Free virtual estimate from your phone. Fifteen minutes, no obligation.